![]() |
|
|
|
|
|
|
|
December 2005 Quarterly Report |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Report on Activities for the Quarter ended 31 December 2005
1. BEACONSFIELD MINE JOINT VENTURE (BMJV) (Beaconsfield Gold Direct Interest 48.49%) 1.1 OPERATING PERFORMANCE As previously announced, gold production from the Beaconsfield Mine was disrupted following a seismic event on 26th October. Production of 19,675 ounces was consequently lower than for the September 2005 quarter (28,083 ounces). Immediately following the event, mine management suspended production from certain high grade stopes and implemented independent geotechnical and mining reviews. Grade dropped to 11.8g/t compared to 15.7g/t in the previous quarter because of the lack of access to high grade stopes. Stoping activities were gradually recommenced as ground support was upgraded where required, but a significant number of high grade stopes remained inaccessible throughout the quarter. The availability of low grade stopes in areas not significantly affected by seismicity, and increased sill driving, allowed ore hoisted to improve to 60,567 tonnes (September 2005 quarter: 55,593 tonnes). Late in the quarter, the geotechnical and mining reviews were completed. A revised mining method, known as “checkerboarding”, is being introduced and additional ground support is being used in seismically prone areas. This mining method is a variation on the previously employed half-upper method but follows a different sequence to avoid the creation of narrow, highly stressed crownpillars. The new method is not expected to lead to material changes in either production rates or costs and most of the deferred high grade stopes are now available for mining. There has been no permanent loss of gold as a result of the seismic event. Mill throughput was constrained by repeated secondary crusher failures and the troublesome unit was replaced in January2006. Spare mill capacity will now allow the ore stockpiles, which increased by7,121 tonnes during the quarter, to be reduced to more normal levels. The mine access decline advanced by only 55 metres to a depth of 1,090 metres below surface. After October 26, the decline development crew was reallocated to ore mining activities to accelerate the resumption of normal production. 1,987 tonnes of waste rock were hoisted to surface early in the quarter. The balance was utilised underground as stope backfill, together with 1,552 tonnes of sand-fill. The mine did not intersect any significant water inflows. Development and stoping advanced unimpeded by water inflows. The pumping rate decreased marginally to be at 60 litres per second in December Production Summary
(1) Mill reconciled head grade. 1.2 EXPENDITURE Operating, Capital and Total Cash Expenditure
(1) Including underground diamond drilling costs. Direct operating costs of $519 per ounce were significantly impacted by the lower gold production resulting from the lower mined grade and the secondary crusher problems in the mill (September 2005 quarter $413 per ounce). Cost reduction and capital deferral measures implemented to mitigate the impact of the reduced production saw cash expenditure reduced by more than $2 million compared to the September 2005 quarter. In terms of cost per tonne milled, the December 2005 quarter figure of $191 was lower than the previous quarter ($195 per tonne). Capital expenditure fell to $1.0 million (September 2005 quarter: $2.0 million) with completion of the extensive ore reserve diamond drilling program, limited progress in the mine access decline and the deferral of projects to mitigate the impact of the seismic event. 1.3 UNDERGROUND DRILLING OF THE TASMANIA REEF
Notes: During the September 2005 quarter, Holes F110 and F112 hadbeen drilled but assayresults were not available. (1)The co-ordinate system is defined such that the centre of the Hart Shaft has the co-ordinates 2600mE, 5000mN and the grid is orientedat AMG north plus 47.5º. 1.4 ORE RESERVES/RESOURCES 1.4.1 As at 31 December 2005 The reserves and resources for the Tasmania Reef as at 31 December 2005 have been estimated by Allstate as Manager of the BMJV as follows:
The Proved and Probable Reserves were estimated from the Measured and Indicated Resources, but exclude Indicated Resources of 159,000 tonnes at 19.2 g/t gold (98,000 ounces contained gold) contained in the F21 Zone. Following the completion of diamond drilling in the 840E Zone, resources in this area have been upgraded from the Inferred category to the Indicated category,estimated at 305,000 tonnes at 9.8 g/t gold (96,000 ounces contained gold). Work is ongoing to optimise the mining of the 840E and F21 zone resources. This detailed optimisation study is expected to be completed by April 2006. 1.4.2 Reconciliation between 30 June 2005 and 31 December 2005 Ore Reserves Total gold milled in the six months to 31 December 2005 was estimated to be 50,458 ounces. Subtracting this total from the ore reserves at June 2005 (285,000 ounces) gives 234,542 ounces. As the ore reserves at 31 December 2005 were 233,000 ounces, there was no material decrease in ore reserves over the six months, other than allowing for mining depletion. As noted above, the updated reserves contain no allowance for the F21 and 840E Zones which have been estimated by Allstate to currently have an Indicated Resource of 194,000 ounces of contained gold. 1.4.3 Resources Additional to Reserves At 30 June 2005, resources additional to reserves were 458,000 tonnes at 12.2 g/t gold, containing179,000 ounces. At 31 December 2005, resources additional to reserves for the Tasmania Reef were 523,000 tonnes at 13.1 g/t gold, containing 220,000 ounces of gold.
Following the completion of the F Series resource diamond drilling programme in September 2005, two holes were drilled from the hangingwall drill drive on the 870mL to investigate the possibility of an economic Southern Reef paralleling the Tasmania Reef in the hangingwall. Evidence for the Southern Reef had previously been seen in development on the 375mL and in Hole C13 drilled from the 300mL and several surface drill holes. Holes F113 and F114 totalling 677.6m were completed in the quarter, but no significant structures or mineralisation were encountered. 1.6 BMJV REGIONAL EXPLORATION Surface diamond drilling commenced at Middle Arm Gorge late in the quarter and hole B52 reached a depth of 29m prior to the Christmas break. This six-month program aims to investigate a possible separate reef structure paralleling the Tasmania Reef. The target is conceptual based on a model of the Tasmania Reef, with a target depth in the first hole expected between 400 600m. An initial programme of 3 to 4 holes is planned. Middle Arm Gorge is located around 2 km south of the Tasmania Reef. Follow-up work on the historical Salisbury Gold Field is also planned. 1.7 ARBITRATION AWARD As previously reported, Beaconsfield Gold is expecting to receive approximately $6.3 million, being its 48.49% share of a $13 million in-principle settlement agreed with the insurer of the plant design and construction contractor, subject to the insurer being provided with various releases. 50% of any proceeds received by Beaconsfield Gold in this matter are required to be applied against a contingent liability in respect of interest set aside by a former secured creditor. Negotiations to obtain the required releases progressed throughout the quarter. 1.8 ALLSTATE EXPLORATIONS NL (“Allstate”) CLAIM AGAINST LEGAL ADVISER The previously reported claim by Allstate, on its own behalf and as Manager of the BMJV, seeking damages for professional negligence against a legal firm continued to be progressed. There were no significant developments during the quarter.
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Quarter Ending
|
BMJV Gold Production (oz)
|
BCD 48.49% Production (oz)
|
Net Gold Book Proceeds ($m)
|
Average BCD Proceeds ($/oz)
|
||||||||||||||||||||
| 2005 Year |
125,795 |
60,998 |
34.102 |
559 |
||||||||||||||||||||
| 2005 September |
28,083 |
13,618 |
7.681 |
564 |
||||||||||||||||||||
| 2005 December |
19,675 | 9,540 | 5.817 | 610 |
3.1.3 Spot Gold Prices
In the first half of calendar 2005, the spot gold price was around A$550 per ounce. The spot price of gold has increased dramatically since that time and is currently (early calendar 2006) around A$740 per ounce, an increase of around A$190 per ounce.
Beaconsfield Gold’s share of BMJV gold resources at 31 December 2005 was approximately 223,500 ounces. The increase of around A$190 per ounce therefore has increased the potential value of Beaconsfield Gold’s gold resources by around A$42 million. This in turn improves the likelihood that the majority of the resources additional to reserves will be converted into reserves over time. Additionally,the higher spot gold price makes it more likely that the proposed deep drilling program for the Tasmania Reef (to test between 1200mand 1500m depth) will also result in increased reserves over time.
3.2 CASH POSITION
At 31 December 2005, total effective cash held by the Company was approximately $3.7 million, excluding the $3.15 million of pending cash from the in-principle settlement with the BBR insurer.
3.3 CLAIM AGAINST ALLSTATE
As previously reported, Beaconsfield Gold lodged a Proof of Debt (“POD”) with the Allstate Deed Administrators for $29,271,854 plus interest, representing 48.49 % of the damages awarded to the BMJV participants in the claim against the plant design and construction contractor. The Allstate Deed Administrators subsequently rejected the POD and Beaconsfield Gold has filed an application in the Supreme Court of Victoria appealing against the rejection. This matter continues to be progressed. A directions hearing is scheduled for February 2006.
3.4 BEACONSFIELD GOLD ISSUED SECURITIES AT 30 SEPTEMBER 2005
| Type of Securities |
Number of Securities |
ASX Code |
| Fully-Paid Ordinary Shares |
153,227,481 |
BCD |
| Unlisted Convertible Notes ($0.30 each by 30/6/2006) |
666,667 |
|
| BankWest Unlisted Options ($0.2823 each by 30/6/2006) |
6,500,000 |
|
| Unlisted Employee Options ($0.374 by 1/9/2010) | 800,000 | |
| Unlisted Partly-Paid Shares ($0.35 paid to $0.01) |
2,450,000 |
|
| Unlisted Partly-Paid Shares ($0.40 paid to $0.01) | 1,000,000 |
3.5 TENEMENTS
Beaconsfield Gold has interests in the following tenements.
| Description |
Licence Number |
Area |
% Interest |
State |
| Beaconsfield Consolidated Mining Lease |
1767 P/M |
594 hectares |
48.49 |
Tas. |
| Beaconsfield Retention Licence |
RL 1/1999 |
2 sq km |
48.49 |
Tas. |
| Salisbury Hill Exploration Licence |
EL 20/1994 |
12 sq km |
48.49 |
Tas. |
| Beaconsfield Exploration Licence |
EL 12/1999 |
8 sq km |
100.0 |
Tas. |
| North Beaconsfield Exploration Licence |
EL 27/2000 |
3 sq km |
100.0 |
Tas. |
| Pease Creek Exploration Licence |
EL 30/1997 |
5 sq km |
100.0 |
Tas. |
| Beaconsfield Exploration Licence |
EL 7/2000 |
19 sq km |
100.0 |
Tas. |
| Stavely Exploration License (Option*) |
EL 4556 |
370 sq km |
100.0(a) |
Vic. |
| Stavely Sth Expl. License Application | ELA 4929 | 25 sq km | 100.0(b) | Vic. |
| Dunkeld Expl. License Application | ELA 4930 | 28 sq km | 100.0(b) | Vic. |
| Watgania Expl. License Application | ELA 4931 | 512 sq km | 100.0(b) | Vic. |
| Bolac Expl. License Application | ELA 4932 | 186 sq km | 100.0(b) | Vic. |
| North Dunkeld Exploration License | EL 4514 | 60 sq km | 100.0(c) | Vic. |
(a) BCD has an option to acquire 100% interest, subject to a 3% net smelter return royalty.
(b) DPI has advised priority on these applications.
(c) BCD has agreed to purchase outright from New Holland Mining for $20,000.
3.6 INTERNET
Shareholders are invited to visit the Company's website to view all ASX releases (including all quarterly and annual reports), historical information relating to the Beaconsfield Mine, and Beaconsfield Gold NL corporate information: www.beaconsfieldgold.com.au
Shareholders who wish to receive Beaconsfield Gold ASX releases by e-mail are encouraged to contact the Company on: beaconsfieldgold@bigpond.com
| For further information contact: |
|
| Bill Colvin - Chief Executive Officer e: bill.colvin@beaconsfieldgold.com.au |
Brian Coulter - Company Secretary e: brian.coulter@beaconsfieldgold.com.au |
| Beaconsfield Gold NL |
|
| t: 61-3-9909-7401 e: beaconsfieldgold@bigpond.com w: www.beaconsfieldgold.com.au |
|
Home | Corporate | Investor Centre | Media Centre | Projects | Contact Us