|
|
Report on Activities for the Quarter ended 30 September 2004
The Quarterly Report is also available as a PDF File For Printing & Offline Viewing
Click here for PDF File (180K)
|
To view the PDF File you will require Acrobat Reader
You can download your copy of Acrobat Reader Here -
|
 |
HIGHLIGHTS
- BMJV gold production for the September 2004 quarter was 34,045 ounces (June 2004 quarter 30,848 ounces). 55,549 tonnes of ore (56,226 tonnes previous quarter) were milled at an average head grade of 19.4 g/t gold (18.4 g/t previous quarter) and an average gold recovery of 98.0% (92.6% previous quarter), excluding changes in gold in circuit.
- BMJV direct operating expenditure per ounce for the quarter was A$325 per ounce (A$314 previous quarter) versus gold revenue for Beaconsfield Gold of A$513 per ounce (A$570 per ounce previous quarter).
- Beaconsfield Gold cash flow from its 48.49% direct interest in the BMJV for the quarter was approximately $2.1 million ($2.8 million previous quarter).
- BMJV underground drilling program continuing with drilling commencing from two cuddies established to target new ore reserves below the 840 metre level east zone and also the F21 eastern zone above 1200 metres depth.
- Beaconsfield Gold recommenced drilling on its 100% owned exploration tenements at the end of the quarter. The first hole at North Pease Creek encountered Ordovician Mine Sequence stratigraphy under Tertiary cover 3 km north-west of the Beaconsfield Mine. A fine fractured stockwork at the base of the hole carried anomalous gold and arsenic.
- Beaconsfield Gold audited profit for the 2004 year (no tax payable) was $11.7 million after providing for depreciation and amortisation of $6.3 million.
- During the quarter, Beaconsfield Gold fully repaid its remaining 48.49% share of the total owing to the providers of goods and services to the Beaconsfield Mine who had their invoices frozen when Allstate, the Manager of the BMJV, went into administration on 8 June 2001.
- At the end of the quarter, BankWest secured debt was $4.2 million against which Beaconsfield Gold held $6.8 million in cash, of which $5.7 million was held in BankWest accounts with restricted access.
|
KPI SUMMARY FOR 12 MONTHS ENDING 30 SEPTEMBER 2004
Key performance indicators for the Beaconsfield Mine Joint Venture (BMJV) and Beaconsfield Gold (BCD) for the 12 months ending 30 September 2004 are as follows:
| _BMJV Ore Mined (hoisted) |
228,540 tonnes |
| _BMJV Ore Milled |
229,611 tonnes |
| _BMJV Head Grade |
20.4 g/t gold |
| _BMJV Gold Milled |
150,832 ounces |
| _BMJV Gold Recovery (excluding changes in gold in circuit) |
94.6 % |
| _BMJV Gold Produced |
142,619 ounces |
| _BMJV Gravity Gold Produced |
80,329 ounces |
| _BMJV Bacterial Oxidation Leach Gold Produced |
62,290 ounces |
| _BMJV % of Gold Produced by Gravity Means |
56 % |
| _BMJV Direct Operating Expenditure: |
$39.7 million |
|
$173/tonne milled |
|
$278/ounce produced |
| _BMJV Capital Expenditure (including ore reserve drilling): |
$8.2 million |
|
$36/tonne milled |
|
$58/ounce produced |
| _BMJV Direct Operating plus Capital Expenditure: |
$47.9 million |
|
$209/tonne milled |
|
$336/ounce produced |
| _BMJV Effective Cash at 30 September 2004 |
$4.5 million |
|
|
|
|
| _BCD 48.49% Share of Gold Production |
69,156 ounces |
| _BCD Revenue from Gold Sales: |
$37.4 million |
|
$541/ounce produced |
| _BCD 48.49% Share Direct Operating plus Capital Expenditure |
$23.2 million |
| _BCD Cash Flow from its 48.49% Interest in the BMJV (1): |
$14.2 million |
|
$205/ounce produced |
| _BCD BankWest Debt at 30 September 2004 |
$4.2 million |
| _BCD Total Cash excluding BMJV Cash at 30 September 2004 |
$6.8 million |
| _BCD Convertible Notes Debt (7.133 million at $0.30 each) |
$2.1 million |
| _BCD 48.49% Share of BMJV Cash at 30 September 2004 |
$2.2 million |
|
(1) Before BCD corporate and debt servicing costs.
1. BEACONSFIELD MINE JOINT VENTURE (BMJV) (Beaconsfield Gold Direct Interest 48.49%)
The participants in the unincorporated BMJV, which operates the Beaconsfield Mine at Beaconsfield in north-east Tasmania, are the Allstate group with a 51.51% interest and the Beaconsfield Gold group with a 48.49% interest. Allstate, with the higher interest, is Manager of the BMJV and the BMJV Mine Manager and all the personnel reporting to him are employed by Allstate.
Joint Administrators (Michael Ryan and Tony Woodings of chartered accounting firm, Taylor Woodings, based in Perth, Western Australia) were appointed to Allstate on 8 June 2001 and became Joint Deed Administrators when Allstate creditors approved a Deed of Company Arrangement in late 2001. A Receiver and Manager was appointed to Beaconsfield Gold on 25 June 2001 and retired on 12 March 2004.
1.1 UNDERGROUND DRILLING OF THE TASMANIA REEF
The current BMJV underground diamond drilling program (F series) commenced on 13 December 2003 and is now planned to be completed in June 2005.
Assay results received to date are as follows:

The drilling from the Trevor and South Trevor cuddies in the hangingwall of the Tasmania Reef at the 870 metre level established that a previously unknown fold in the stratigraphy hosting the Tasmania Reef has resulted in a strike offset of the mineralisation of approximately 150 metres to the east from around 1,000 metres depth.
Two new drilling cuddies, at Middle East Trevor, were established approximately 130 metres to the east of the Trevor and South Trevor cuddies on the 870 metre level towards the end of the September quarter. The great majority of the balance of the drilling program will now be carried out by two diamond drilling rigs operating from these cuddies through to June 2005. The target of the drilling will be to establish new ore reserves in two areas: (1) below the 840 metre level east zone and (2) in the F21 resource zone above 1200 metres depth.
In addition, it is planned to drill a total of nine intersections from three primary holes, employing navi drilling, below the F21 resource zone between 1200 and 1400 metres depth. The first of these nine holes, F53, is currently being drilled.
1.2 MINE PERFORMANCE
Ore production at the end of the quarter was available from over 10 levels throughout the mine, down to the 965 metre level, allowing significant flexibility in mine scheduling. The decline / waste development layout and the modified ½ Upper / Avoca mining method continued to provide operating benefits and efficiencies. Decline advance during the quarter totalled 185 metres with the face of the decline 1,005 metres below surface at 30 September 2004.
Production Summary

The Hart Shaft continued to perform well during the quarter with 55,833 tonnes of ore and 35,251 tonnes of waste (total material 91,084 tonnes) being hoisted. An additional 7,886 tonnes of waste rock were not hoisted, being utilised underground as stope backfill. A further 2,206 tonnes of "sand fill", a coarser fraction of the mill tailings, were also pumped underground and used as stope backfill.
Gold Production

The average September 2004 quarter reconciled head grade of 19.4 g/t gold was 1.0 g/t or 5% better than for the June 2004 quarter.
Ore treatment plant gold recovery for the September 2004 quarter, excluding changes in gold in circuit, was 98.0% compared with the June 2004 quarter figure of 92.6%. There was a build up in gold in circuit at the end of June 2004 due to an unusual electrical failure in the ore treatment plant in that month and that temporary build up in gold in circuit inflated the recovery figure in the subsequent September 2004 quarter.
Gold production for the September 2004 quarter was 34,045 ounces, 3,197 ounces or 10% greater than the June 2004 quarter result of 30,848 ounces. The percentage of gold production recovered by gravity processes during the quarter was approximately 51%.
1.3 BMJV EXPENDITURE

Direct operating expenditure for the September 2004 quarter was $11.062 million, 14% higher than for the June 2004 quarter ($9.682 million). Mining costs were abnormally high, being 22% higher than for the June quarter.
Capital expenditure for the September 2004 quarter was $2.062 million (June 2004 quarter was $2.103 million). The main abnormal capital expenditure activity continued to be the extensive ore reserve diamond drilling program.
1.4 EXPLORATION JOINT VENTURE BETWEEN DDV AND THE BMJV
No field work was carried out by DDV on the BMJV exploration tenements during the quarter.
1.5 ARBITRATION AWARD
As previously reported in January 2004, an arbitration award was made in favour of the BMJV participants (Beaconsfield Gold group 48.49% and Allstate group 51.51%) against ACN 005 585 795 Pty Ltd (formerly Brown & Root Engineering & Construction Pty Ltd ("BREC")) and Batepro Australia Pty Ltd ACN 009 006 777 ("BA"). The arbitrator, Mr J Tyrill, found that BREC and BA are jointly and severally liable to the BMJV participants for $60,366,785 together with interest after 17 January 2004 at the rate of $29,292 per week. The Arbitrator also found that the cross claims by BREC and BA against the BMJV participants fail.
On 30 April 2004, Administrators were appointed to BREC and the Administrators were subsequently appointed the liquidators of BREC on 1 July 2004. On 7 June 2004, liquidators were appointed to BA. The Deed Administrators of the Allstate group, together with the Beaconsfield Gold group, are continuing to deal with the liquidators of BREC and BA in regard to the arbitration award.
2. BEACONSFIELD GOLD CORPORATE
2.1 EXPLORATION OF BEACONSFIELD GOLD'S 100% OWNED TENEMENTS
In the March and June 2004 quarters, Beaconsfield Gold generated various drill targets on its 100% owned exploration tenements based on re-interpreted geophysics and a program of geochemical soil sampling. Drilling of these targets is to be carried out during the 2004/2005 year.
Several drill targets to the east and north-east of the Beaconsfield Mine are based on interpreted faults cutting across favourable stratigraphy with supporting anomalous soil geochemistry.
Another 100% owned target, North Pease Creek, lies north-west of the BMJV retention licence RL 99/2001 which contains the Pease Creek mineralisation discovered in previous years by the BMJV. The prospective corridor of favourable stratigraphy which hosts the Tasmania Reef 3 km to the south-east is considered likely to continue north-west of Pease Creek under Tertiary cover rocks and the re-interpreted geophysics indicates the presence of cross-cutting faulting on the Beaconsfield Gold tenement.
The first North Pease Creek hole, NPC-1, was drilled at the end of the quarter. Collared approximately 400 metres north-west of the Pease Creek mineralisation, within EL 27/2000, the hole intersected 73 metres of semi-consolidated Tertiary sediments. As predicted, it then entered Ordovician Eaglehawk Gully Formation sandstones, which correlate with the upper division of the Mine Sequence in the Beaconsfield Mine. The hole had to be terminated at 102 metres due to the overlying Tertiary sediments collapsing. The basal 4 metres (98 - 102 metres) consisted of a fine fractured stockwork carrying minor gold (up to 0.3 ppm or 0.3 g/t) and arsenic (up to 539 ppm).
2.2 GOLD HEDGING FOR BEACONSFIELD GOLD
The company initially sold forward 240,000 ounces of gold in October 1998 in a hedging arrangement with BankWest. The remaining hedge book at 30 September 2004 was 26,912 ounces with deliveries out to May 2005 at an average delivered price of A$571 per ounce.
The marked-to-market value of the hedge book at 30 September 2004, when the spot price of gold was A$577.59 per ounce, was negative $0.5 million.
2.2.1 Gold Hedging as a Percentage of Ore Reserves
The BMJV ore reserves as at 30 June 2004 were 381,000 ounces so that Beaconsfield Gold's 48.49% direct interest was approximately 184,700 ounces. As a percentage of those ore reserves therefore, Beaconsfield Gold at 30 September 2004 was only approximately 15% hedged.
2.2.2 Average Received Price per Ounce
Compared with its hedge book, Beaconsfield Gold has received higher prices on average as a result of generally favourable gold lease rates and selling spot when the spot price is favourable. Total net gold book proceeds and effective average received price per ounce of production are approximated in the following table. The average price received in the September 2004 quarter was lower than in previous quarters because the Company delivered into its lowest priced hedges, A$485 per ounce, during the quarter. With the remainder of the hedge book averaging A$571 per ounce, close to current spot prices, a significantly better average price will be achieved in the December 2004 quarter.
Average Proceeds per Ounce of Production
2.3 BEACONSFIELD GOLD CASH FLOW FROM ITS 48.49% DIRECT BMJV INTEREST
Cash flow accruing to Beaconsfield Gold from its 48.49% direct interest in the BMJV, before BCD corporate and debt servicing costs, is approximated in the following table.
Beaconsfield Gold Cash Flow from its 48.49% Direct Interest in the BMJV

2.4 FULL REPAYMENT OF DEBT TO PRE - 8 JUNE 2001 ALLSTATE TRADE CREDITORS
Prior to coming out of receivership in March 2004, Beaconsfield Gold owed $2,620,927 to Allstate Explorations NL (Subject to Deed of Company Arrangement). This amount was the Company's remaining 48.49% share of the total owing to the unsecured trade creditors of Allstate, the providers of goods and services to the Beaconsfield Mine who had had their invoices frozen when Allstate, the Manager of the BMJV, went into administration on 8 June 2001.
Two repayments of $327,616 each were made by the Company on 12 March 2004 and 5 July 2004. A further repayment of $400,000 was made on 6 August 2004 and the remaining balance of $1,565,715 was repaid on 7 September 2004.
2.5 BANK DEBT AND CASH POSITION
At the end of the September quarter, BankWest secured debt was approximately $4.2 million against which the Company held approximately $6.8 million in cash, of which $5.7 million was held in BankWest accounts with restricted access.
Three banks are currently completing due diligence with the intention of making credit-approved offers to Beaconsfield Gold for hedging, revolving credit and guarantee facilities to replace the BankWest facilities. The Company expects to be able to decide on a new bank within a month.
2.6 CURRENT BEACONSFIELD GOLD ISSUED SECURITIES
| Type of Securities |
Number of Securities |
ASX Code |
Fully-Paid Ordinary Shares
Unlisted Convertible Notes ($0.30 each by 30/6/2006)
BankWest Unlisted Options ($0.2823 each by 30/6/2006)
Unlisted Partly-Paid Shares ($0.35 paid to $0.01) |
143,897,309
7,133,333
6,500,000
3,850,000 |
BCD |
2.7 TENEMENTS
Beaconsfield Gold has interests in the following tenements in the Beaconsfield area.
2.7.1 BMJV Tenements (Beaconsfield Gold 48.49% Direct Interest)
| Description |
Licence Number |
Area |
% Interest |
Beaconsfield Consolidated Mining Lease
Beaconsfield Retention Licence
Salisbury Hill Exploration Licence |
1767 P/M
RL 99/2001
EL 20/1994 |
594 hectares
2 sq km
21 sq km |
48.49
48.49
48.49 |
2.7.2 Beaconsfield Gold 100% Owned Exploration Licences
| Description |
Licence Number |
Area |
% Interest |
Beaconsfield Exploration Licence
North Beaconsfield Exploration Licence
Pease Creek Exploration Licence
Beaconsfield Exploration Licence |
EL 12/1999
EL 27/2000
EL 30/1997
EL 07/2000 |
8 sq km
3 sq km
5 sq km
19 sq km |
100.0
100.0
100.0
100.0
|
2.8 INTERNET
Shareholders are reminded that ASX releases (including all quarterly and annual reports), can be seen on the Company's web site: www.beaconsfieldgold.com.au
Shareholders who wish to receive Beaconsfield Gold ASX releases by e-mail are encouraged to contact the Company on: beaconsfieldgold@bigpond.com
Yours faithfully
Mike Trumbull
B.E. (Mining, First Class Honours), M.B.A., F.AusIMM
Managing Director
|